Termokos is receiving applications until the end of this month from potential contractors, for the first lot. It envisages the construction of a 30 MW solar thermal plant near the village of Shkabaj (Orlović). The facility in Obiliq (Obilić) municipality is for the district heating system in Prishtina.
The operator, Termokos, is owned by the Municipality of Prishtina, the capital city. They secured most of the funds for Solar4Kosovo 2 – Solar District Heating through the European Union’s Western Balkans Investment Framework (WBIF), Germany’s KfW Development Bank and the European Bank for Reconstruction and Development.
The estimated time for completion is 30 months plus a six-month commissioning phase. After several years of preparation, Kosovo* is moving ahead with the largest solar thermal project for district heating in the Western Balkans. The operator, Termokos, is owned by the Municipality of Prishtina, the capital city.
The other part of the Solar4Kosovo 2 – Solar District Heating project is for a network extension with 20 MW more heat from a coal-fired power plant Pre-qualification documents can be requested from the tender agent via email at [email protected].
Our home solar PV systems and energy storage products are engineered for reliability, safety, and efficient deployment in Polish conditions. All systems include comprehensive monitoring and control with remote management capabilities.
BigSolar Prishtina: Innovative solar district heating solution improves air quality and reduces CO₂ emissions.
Learn MoreGrCF2 W2 E2 Pristina Solar District Heating Explore this section Overview The Project consist of the construction of a solar thermal plant with a 30 MW capacity to provide …
Learn MoreBy increasing the share and capacity of solar energy in power generation, the project will contribute to energy supply security, a faster green transition and economic growth in the region. Upon completion, the plant is expected to …
Learn MoreBy increasing the share and capacity of solar energy in power generation, the project will contribute to energy supply security, a faster green transition and economic growth in the …
Learn MoreResults of the study show that solar resources are much more suitable for installation in the urban area of Prishtina and produce much more power than wind resources, …
Learn MoreKosovo has prioritized the development of solar and wind resources under the Energy Strategy 2022-2031, with the construction of a 100 MW solar PV plant being devised among numerous priorities …
Learn MoreDistrict heating utility Termokos is seeking a contractor to build a 30 MW solar thermal facility outside Prishtina in Kosovo*.
Learn MoreSë bashku për një Prishtinë më të gjelbër Një projekt zhvillimor i Republikës së Kosovës, i bashkëfinancuar nga Republika Federale Gjermane përmes KfW dhe nga Bashkimi …
Learn MoreDistrict heating utility Termokos is seeking a contractor to build a 30 MW solar thermal facility outside Prishtina in Kosovo*. The estimated time for completion is 30 months …
Learn MoreThe paper aims to analyze the potential of solar and wind resources in these three locations and also identifying which of these two resources is more efficient when installed in …
Learn MoreKEK is receiving bids within the prequalifications call for its Solar4Kosovo photovoltaic project until January 22.
Learn MoreKosovo has prioritized the development of solar and wind resources under the Energy Strategy 2022-2031, with the construction of a 100 MW solar PV plant being devised …
Learn MoreLatest developments in solar PV technology, energy storage advancements, commercial power solutions, and industry insights from our team of renewable energy experts across Poland.
Contact our technical sales team for home solar PV systems and energy storage solutions in Poland. We provide customized quotations based on your specific project requirements and energy needs.
STAN BESS Sp. z o.o. ul. Elektryczna 15, 00-001 Warsaw, Poland